PM Scheduler
May 2026
UpcomingOpenIn ProgressClosed
Sun
Mon
Tue
Wed
Thu
Fri
Sat
26
27
28
29
30
1
Monthly AHU Filter Change
AHU-12 (L15-L23)
Lift Weekly Mechanical
Goods Lift L-04
2
Main Gate Gantry Test
Gantry Barrier GB-03
3
4
Genset Weekly Run Test
Genset GS-01
5
Quarterly Fire Alarm Test
Fire Alarm Panel FAP-01
AHU Belt Tension Check
AHU-12
6
Cooling Tower Dosing
Cooling Tower CT-01
7
Fire Pump Weekly Run
Fire Pump FP-01
8
MCCB Tightening
MSB-3 Switch Room
Lift Weekly Mechanical
Goods Lift L-04
9
Main Gate Gantry Test
Gantry Barrier GB-03
10
11
Genset Weekly Run Test
Genset GS-01
12
AHU Belt Tension Check
AHU-12
13
UPS Load Bank Test
UPS UPS-01
Cooling Tower Dosing
Cooling Tower CT-01
14
Fire Pump Weekly Run
Fire Pump FP-01
15
Sump Pump Quarterly
Sump Pump SP-2
Lift Weekly Mechanical
Goods Lift L-04
16
Main Gate Gantry Test
Gantry Barrier GB-03
17
18
Genset Weekly Run Test
Genset GS-01
19
AHU Belt Tension Check
AHU-12
20
Emergency Lighting Test
All Floors
Cooling Tower Dosing
Cooling Tower CT-01
21
Fire Pump Weekly Run
Fire Pump FP-01
22
Lift Weekly Mechanical
Goods Lift L-04
23
Main Gate Gantry Test
Gantry Barrier GB-03
24
25
Annual Lift PM
Goods Lift L-02
Genset Weekly Run Test
Genset GS-01
26
AHU Belt Tension Check
AHU-12
27
Cooling Tower Dosing
Cooling Tower CT-01
28
Fire Pump Weekly Run
Fire Pump FP-01
29
Fire Extinguisher Servicing
All FE Cabinets
Lift Weekly Mechanical
Goods Lift L-04
30
Main Gate Gantry Test
Gantry Barrier GB-03
31
1
2
3
4
5
6